Inside!

Stan, Brandon, and Josh have been working hard to install the tongue and groove pine for the interior walls. All the walls are finished including the 4 x 6 decorative beams along the ceiling and gable end of the living room/kitchen.

Jason and his crew were able to stain the majority of the wood, as well as paint the wallboard in the bedrooms, closets, bathroom, loft, and one accent wall in the living room.











The oak flooring has also arrived and begun its acclimation. Hopefully we can start intalling it in about three weeks. It will match the beams and trim stain nicely.